As a prime consultant, KSE is conducting special inspections for civil, utility, and roadway elements as well as pile and foundation inspections for the new Terminal One (T1) at JFK International Airport in Queens, New York.
The new terminal facility will incorporate the current and former sites of Terminals 1, 2 and 3 into a massive, 2.5 million-square-foot international terminal that will anchor the south side of the airport. Construction of the new terminal will take place in various phases, beginning with the construction of the new arrivals and departures hall and the first set of new gates. When fully complete in 2030, the new Terminal One will feature 23 gates, a redesigned check-in hall, and overhauled arrival spaces.
KSE’s scope of work includes performing inspection services for Structural Steel Welding/ High Strength Bolting, Concrete Cast in Place/Rebar/Sampling and Testing/Mix Design/Lab Breaks, Masonry/Grout Testing, fuel oil/piping systems, Excavation/ Sheet/ Shoring, Post Installed Anchors, Soil/Geotechnical/Lab Testing, in-place density of soil and asphalt, as well as Footings and Foundations.
In the laboratory, KSE is performing sieve analysis, Atterberg limits, hydrometer, Ph, proctor, and classification tests on soil among other index and engineering tests.
#2591